News
Since the beginning of this year our company has been working on the project “Construction of the two substations 110/10 kV “Astana-1” and “Astana-2” with power line 110 kV” in Shimkent (Kazakhstan).
Up to now we have installed 100 of straight-through and 50 cross-bonding joints on the site. The works are fulfilled by local contractor Electromontaj under the supervision of our staff.
Delivery and installation of outdoor terminations MKB 252 for STERLITE POWER TRANSMISSION project: “220 kV Accessories for Amargarh project: NRSS” (India), 08 August 2018We produced and successfully tested outdoor terminations 220 kV for project of STERLITE POWER TRANSMISSION (India).
Under the contract we supply 25 pcs. of MKB 252 to the Customer.
These cable accessories will be used for the construction of substation 400/220 kV “Amargarh”, a link for 3 transmission lines. The substation and transmission lines will create passageway for power transmission to Kashmir valley. This project is the largest in the whole history of India.
Immediately after the delivery of this equipment to the site, our staff is going to install the cable accessories on a cable with a shield of corrugated aluminum manufactured by STERLITE POWER TRANSMISSION.
This contract for delivery of outdoor terminations is the first for us in India, it’s the important step in the region and in our cooperation with a local cable provider.
Substation "Cunco", Chili, 24 May 2018Every year we expand our presence, realizing the projects on new territories. So, in May 2018 we successfully installed the cable accessories at the SS “Cunco”, Chili: 9 outdoor terminations MKB 126 and 9 GIS sealing ends EHSVS 123 produced by Süedkabel. This is the first contract with our Chili’s partner - Best Energy SpA & it’s opening new opportunities for us in the South America region.
Training in Thailand, 10 May 2018At the end of April 2018 our specialists successfully trained Jointers of the local installation company and the distribution utility PEA (Bangkok, Thailand). According to the contract installation of the accessories will be done by certified installators of the customer under the supervision of Arkasil SK. Installation of 24 outdoor terminations will start in May.
You can find photo here.